Once you have completed photogrammetry, and have produced an Alembic, ST Map(s), and optional Mask Mesh, you can run the PROCESS step to create PBR textures.

Configure Processing

Click ‘Queue’ to add the selected job to the run queue.

36_process_job_queue.png

The configure window will be launched, with the Process tab selected.

37_process_job_configure.png

Select Presets

The Light system has been pre-filled from when the job was created. It can be replaced with a different preset if necessary.

Note

If the selected light system has a different number of lights to the initial configuration, Marso may not work correctly.

An exposure preset is required to process a job.

38_process_job_exposure.png

Click the exposure preset for your capture system, and click ‘Select’ to confirm.

If you have not yet created an Exposure preset, see:
https://m-xr.atlassian.net/wiki/spaces/MD/pages/486539289/Setup#Exposure-Preset

39_process_job_select_exposure.png

The Light system has been pre-filled from when the job was created. It can be replaced with a different preset if necessary.

Note

If the selected light system has a different number of lights to the initial configuration, Marso may not work correctly.


Provide Geometry

Then provide the paths to the Mesh File and ST Map produced by photogrammetry.

You can optionally provide the path to an additional Mask Mesh file.

41_process_job_geometry.png


Select Shader Workflow

Next check all shader workflows you would like to use textures for.

42_process_job_shaders.png


Texture Export Options

The final settings are:

  • UV Bleed: we recommend leaving this on.

  • UV Resolution: Select the desired UV texture resolution.

    • If multiple are selected, the material will be processed at the highest resolution and smaller textures will be down-sampled from it.

43_process_job_export.pngImage Removed43_process_job_export.pngImage Added


Save Configuration

Clicking Queue to add the job to the processing queue, or Cancel to discard changes.

44_process_job_configure_finish.png

This will return you to the main Marso window, where the selected job is now in the run queue. You should see the configuration you entered in the Details panel.


Run Process

As with the Develop step, clicking ‘Start’ will run all jobs in the queue.

Once Running you can see progress at the bottom of the window.

46_process_job_running.pngImage Removed46_process_job_running.pngImage Added

Panel
panelIconId23f0
panelIcon:alarm_clock:
panelIconText
bgColor#F4F5F7

Processing can take upwards of 8 hours, depending on the mesh size, source photography, export resolution, and the number of cameras and lights. See Processing Times.


Interrupting a Job

A running job can be interrupted with either the Stop/Skip or Pause buttons. Both will keep any progress up to the current step. Pause will return it to the front of the queue, while Skip will remove it from the queue and start processing the next queued item.


When the processing has completed, the ‘Results’ button will become available.

Click ‘Results’ to open explorer in a folder containing textures for your subject

47_process_job_finished.pngImage Removed

Go to Using Results for more on how to use your texture files.

47_process_job_finished.pngImage Added


Failed Jobs

If the processing fails, check the log file listed in the details panel.

If there is no obvious error, go to Help & Support